Taken from the specifications as issued, against the designs they replaced.
Bundaberg Brewing Co.
290 mm slab, N16-200 bottom + N12-200 top
235 mm + 23 kg/m³ SteelX 5:25 + SL81
55 mm off the slab and the top mat deleted. No joints, no visible cracks. Built by Hutchinson Builders.
Sunshine Coast Recreation Centre
Post-tensioned slab on ground
150 mm Liberty™ Slab, SL92 + 18 kg/m³
Post-tensioning removed entirely. No joints and no visible cracks.
Mooloolaba basement
450 mm, N16-200 EW top and bottom
SL81 top and bottom + SteelX
Watertight by design — external membrane deleted.
Defence causeways, Tin Can Bay
200 mm, two layers SL82 mesh
170 mm + 12 kg/m³ SteelX 5:25
30 mm thinner, both mesh layers gone, concrete pump eliminated across 12 causeway slabs.
Rogers Cold Store
35 kg/m³ double hook-end steel fibre
18 kg/m³ SteelX 5:25 + SL81
Half the fibre dosage for a better outcome. Repeat projects in 2023 and 2025.
Culvert apron, Gympie
N12-150 each way
175 mm + 18 kg/m³ + SL82
Bar deleted, mesh retained. Faster placement on a restrained civil element.